History

1987.05
Saemangeum reclamation project promotion plan is released.
1991.11
Saemangeum project enforcement is permitted and begins construction.
2007.04
Inner land development basic plan is established (farmland: 72%, non-farmland: 28%).
2007.12
The Special Act on Promotion of the Saemangeum Project is enacted.
2008.10
Inner land development basic plan is revised (farmland: 30%, non-farmland: 70%).
2010.04
The Saemangeum sea dike is completed(33.9km)
2010.07
Saemangeum waterproof embankment begins construction (agricultural land)
2011.03
Saemangeum Comprehensive development plan (MP) is established.
2012.06
Saemangeum New Port groundbreaking ceremony
2012.12
The Special Act on Promotion and Assistance of Saemangeum Project is enacted.
2013.09
Saemangeum Development and Investment Agency is launched.
2014.09
Saemangeum Basic Plan (MP) is revised.
2015.08
The Special Act on Promotion and Assistance of Saemangeum Project is revised.
2016.02
Office for Government Policy Coordination’ Saemangeum Project Promotion Support Group is formed

History